£1 million overspend from Canterbury City Council in social housing project off Sturry Road

A council has overspent by more than £1 million turning student flats into homes for desperate families - sparking accusations it has “made a dog’s breakfast” of the scheme.

In a deal worth £23 million, Canterbury City Council purchased 44 properties in the Parham Road complex in July 2018.

Some of the homes which are to become council houses as part of the scheme
Some of the homes which are to become council houses as part of the scheme

But the refurbishment of the former student accommodation has been plagued by a number of stumbling blocks and left a bigger hole in council coffers than originally planned.

Documents reveal work to overhaul “unforeseen” leaky roofs and insufficient fire cladding has resulted in a predicted £1,084,000 overspend.

Despite the increased costs, the council is adamant it does not regret the costly purchase and says the lives of 61 families will be transformed as a result.

But opposition leader Cllr Alan Baldock (Lab) has been left stunned by the seven-figure overspend.

“I’m honestly shocked and staggered,” he said.

Cllr Alan Baldock
Cllr Alan Baldock

“They paid top dollar for the properties anyway and an extra £1 million is just huge.

“The whole housing revenue account is a dog’s breakfast. This scheme was meant to be the jewel in the crown but this overspend is taking away refurbishment money from other properties in desperate need.

“It’s mismanagement - this is absolutely not good value for money. The cheapest way to get more social housing is to build your own, but instead they bought these properties, which worked out at above £200,000 per property.

“The public is meant to trust this council with their money and they clearly can’t manage to keep this simple project on budget.”

After purchasing the former student flats, the council uncovered design flaws in the roof construction and discovered the rafters were water-damaged.

The former student homes were bought for £23m
The former student homes were bought for £23m

The authority says building surveys were carried out prior to the acquisition, but water staining to the ceilings was not noted and close inspections were not conducted.

During the investigation to try and ascertain where rainwater was entering the roof in Albert Mews, external cladding was removed and it was established there were no fire stops in the cladding.

It was therefore agreed additional work was required to protect the safety of future tenants.

A report compiled by council officers says the problems would have been very difficult to spot even if more checks were made.

“It is important to note that an intrusive inspection of the cladding prior to acquisition would have been extremely unlikely,” it says.

'It’s mismanagement - this is absolutely not good value for money...'

“The faulty installation was only discovered once the cladding had been stripped back to check for rainwater ingress to the building.”

Despite the £1 million overspend, the council remains pleased with its investment.

Spokesman Rob Davies said: “The decision to go ahead and buy these former student properties and convert them into homes for local families on our waiting list was absolutely the right one and we do not regret it for one minute.

“Twenty units at Parham are also being used as temporary accommodation for homeless families.”

“So far we have been able to provide homes for 24 families and by the time we have finished converting these units, the total will be 61 families. This project has transformed the lives of all these residents, giving them their own home and a safe place to raise a family and live their lives in our wonderful city.”

The authority has overspent by more than a £1 million but insists it was a good purchase
The authority has overspent by more than a £1 million but insists it was a good purchase

“The aims of the project were to increase our housing stock and improve our ability to give a home to people who really need it, and to make use of local housing that would otherwise have slowly degenerated.

“By the time the project is complete, we will have successfully achieved these aims.”